RS20146: Electricity Restructuring Bills: A Comparison of PURPA
Provisions
Amy Abel
Specialist in Energy Policy
Resources, Science, and Industry Division
Jon Shimabukuro
Legislative Attorney
American Law Division
April 7, 1999
Summary
The Public Utility Regulatory Policies Act of 1978 (PURPA) was enacted in part to
augment electric utility generation with more efficiently produced electricity and to
provide equitable rates to electric consumers. Section 210 of PURPA requires a public
utility to purchase power produced by qualifying facilities at the utility's avoided cost:
the incremental cost a utility would have to pay if the utility generated the electricity.
The electric utility industry is moving towards competition, and some argue that §210
of PURPA is no longer needed. Four bills have been introduced in the 106th Congress that
would amend or repeal portions of PURPA: S. 282, introduced by
Senator Mack on Jan. 21, 1999; S. 516, introduced by
Senator Thomas on March 3, 1999; H.R. 667, introduced by
Representative Burr on Feb. 10, 1999; and H.R. 971, introduced by
Representative Walsh on March 3, 1999. This product will be updated as legislative actions
occur. For additional background on PURPA, see CRS Report 98-419, Electricity
Restructuring Background: The Public Utility Regulatory Policies Act of 1978 and the
Energy Policy Act of 1992.
Overview(1)
Electric utilities have been subject to federal and state economic regulation since the
enactment in 1935 of the Federal Power Act (FPA)(2)
and the Public Utility Holding Company Act (PUHCA).(3)
The regulatory framework set up by PUHCA and the FPA, consisting of states regulating
utilities' retail and intrastate activities and the federal government regulating
utilities' interstate and wholesale activities, remained virtually unchanged between 1935
and 1978. As a result of the "oil crises" in the 1970s and concerns about energy
security, legislation was enacted to encourage alternative sources of power.
In 1978, Congress passed the Public Utility Regulatory Policies Act (PURPA)(4) as one of five major pieces of energy
legislation known as "The National Energy Act."(5) PURPA was, in part, intended to augment electric utility
generation with more efficiently produced electricity and to provide equitable rates to
electric consumers. PURPA established several major modifications in the economic
regulation of electric power facilities and substantially injected the federal government
as a regulator into the domain of the economic electric power regulation formerly held by
the states. Under the FPA, federal economic regulation was limited to wholesale rates for
power moving in interstate commerce. With PURPA, the federal role became much more
involved in state rate policies and in regulating utilities.(6)
The original intent of §210 of PURPA was to encourage alternative sources of
electricity beyond traditional generation facilities, without these facilities being
subject to all existing federal and state utility regulations. Perhaps the most
far-reaching provision of PURPA encourages cogeneration(7)
and small power production with so-called qualifying facilities (QFs).(8) QFs are not considered to be utilities, and are therefore
exempt from regulation under PUHCA and the FPA. To be considered a QF, a cogenerator or
small power producer must meet certain FERC rules on fuel use, size, fuel efficiency, and
reliability.
PURPA shifted the price basis for wholesale electricity from the seller's cost to the
purchaser's cost. PURPA indicates that QF power is to be purchased at the
"incremental cost" of alternative energy to the utility.(9) This rate, referred to as the avoided cost, is the likely
costs for both energy and facilities that would have been incurred by the purchasing
utility if that utility had to provide its own generating capacity. These rates are not
based on actual costs incurred in the production of electricity. The determination of
avoided costs has been the responsibility of the states, and procedures to assign avoided
costs have varied greatly between states.
An unintended consequence of PURPA was the introduction of competition into a
"monopoly" industry. The federal government had opened the electricity
generating sector to other entrants and raised questions about the natural monopoly
justification of generation ownership and regulation.(10)
This first incremental change to traditional electricity regulation started a movement
towards a market-oriented approach to electricity supply. Following the enactment of
PURPA, two basic issues prompted calls for further reform: whether to encourage nonutility
generation and whether to permit utility diversification. As a result, the Energy Policy
Act (EPACT)(11) was enacted in 1992
to further increase competition in the electric generating sector. The main effect of the
debate and enactment of EPACT was to continue a reevaluation of traditional electric
utility regulation.
One issue currently before Congress is whether EPACT injected enough competition into
the industry so that PURPA is no longer necessary, or is a more comprehensive approach to
electricity restructuring necessary before PURPA reform should be considered? Some believe
that a repeal of PURPA is necessary before the industry can become truly competitive.
However, others argue that because new PURPA contracts are using market-based pricing, and
in general, states that have moved toward competition have allowed stranded cost recovery
for existing PURPA contracts, federal legislation to repeal or reform §210 of PURPA is
unnecessary. In the 105th Congress, the Administration bill, S. 2287, would have
prospectively repealed section 210 of PURPA. The administration has not released its new
proposal for the 106th Congress.
Legislation
Four bills have been introduced in the 106th Congress that would amend or repeal
portions of PURPA: S. 282,
introduced by Senator Mack on Jan. 21, 1999; S. 516, introduced by
Senator Thomas on March 3, 1999; H.R. 667, introduced by
Representative Burr on Feb. 10, 1999; and H.R. 971, introduced by
Representative Walsh on March 3, 1999. These bills view § 210 of PURPA as outdated, given
the move toward competition in the electric utility industry. These bills are part of a
large ongoing debate on electric utility industry restructuring, and comprehensive bills
that deal with PUHCA reform, retail wheeling as well as PURPA reform, have been introduced
in the 106th Congress.(12)
Existing Contracts. PURPA requires utilities to execute contracts to
purchase power from QFs. As of December 31, 1997, approximately 7% of the U.S. generating
capacity was from QFs. Five states account for almost half of all non-utility capacity:
California (16%), Texas (14%), New York (8%), Virginia (6%), and Florida (5%).(13)
S. 282, H.R. 667, and S. 516 would not affect
existing contracts. However, H.R. 971 would permit a
state regulatory authority to amend existing contracts to ensure that they are reasonable
to consumers and do not exceed the incremental cost to the utility at the time of
delivery. Congress retains the ability to amend existing contracts in this manner. While
the Contracts Clause of the Constitution prohibits a state from passing any law that
impairs the obligation of contracts, the Contracts Clause should not be applicable here
because it does not apply to acts of Congress.(14)
A QF may attempt to argue that the amendment of an existing contract would result in a
taking of its property. The Fifth Amendment to the Constitution states that private
property shall not be taken for public use without just compensation. In this case, a QF
would be denied the payment that was agreed upon with the utility. Nevertheless, it is
unlikely that the QF would be successful. Taking challenges involving government
interference with economic arrangements have generally not been recognized.(15)
Alternately, a QF may contend that any amendment to an existing contract would give
rise to a claim for breach of contract. It is uncertain whether such a claim would be
successful.
Future Contracts. Although S. 282, H.R. 667, and S. 516 would not affect
existing contracts, these bills would prospectively repeal §210 of PURPA, the mandatory
purchase requirement. Under these bills, utilities would not be required to enter into new
contracts with qualifying facilities. As of the date of enactment, H.R. 971 would allow
state regulatory authorities to use fluctuating market rates to determine QF contract
prices.
Stranded Costs. The issue of stranded costs is one of the larger
transitional issues facing the electric utility industry as it moves toward competition.
Stranded costs are defined by recovery proponents as those costs that were legitimately
and prudently incurred under the "old" regulatory regime that are not
economically recoverable under the "new" competitive regime that is being
entered. Alternatively, opponents characterize stranded costs as unrecoverable business
investments that were known to the utilities. Examples of stranded costs include
uneconomic nuclear power plant investments and above-market electricity supply contracts
under PURPA.
S. 282 and H.R. 667 provide for a
federal mandate for full recovery of PURPA related stranded costs. S. 516 does not include a
federal mandate for stranded cost recovery, however, it does allows states to impose
transitional charges to recover stranded cost. H.R. 971 does not include
a provision to recover stranded costs.
Side-by-Side Comparison of PURPA Provisions
| |
S. 282 |
H.R. 667 |
H.R. 971 |
S. 516 |
| Existing Contracts |
Contracts in effect on the date of enactment are not affected by this
bill |
Contracts in effect on the date of enactment are not affected by this
bill |
A state regulatory authority can require changes in existing contracts to
reflect the purchasing utility's incremental cost |
Existing contracts are not affected by this bill |
| Future Contracts |
Prospective repeal of §210 of PURPA. Electric utilities are not required
to enter into new contracts or obligations to purchase or sell electricity or capacity
under §210 of PURPA |
Prospective repeal of §210 of PURPA. Electric utilities are not required
to enter into new contracts or obligations to purchase or sell electricity or capacity
under §210 of PURPA |
States can ensure that rates charged by qualifying small power producers
and qualifying cogenerators are not more than the current incremental cost of the
purchasing utility |
Prospective repeal of §210 of PURPA. Electric utilities are not required
to enter into new contracts or obligations to purchase or sell electricity or capacity
under §210 of PURPA |
| Stranded Costs |
FERC is required to promulgate and enforce regulations to allow utilities
to recover stranded costs associated with PURPA contracts |
FERC is required to promulgate and enforce regulations to allow utilities
to recover stranded costs associated with PURPA contracts |
Does not contain provision to recover stranded costs |
Does not require stranded cost recovery. States may choose to impose
transitional charges to recover stranded costs |
| Effective Date |
Date of enactment |
Date of enactment |
Date of enactment |
Date of enactment |
| Other Relevant Provisions |
|
|
States may establish programs to determine whether qualifying facilities
meet the operating efficiency standards established by FERC |
|
Footnotes
1. (back)For additional information
on electric utility restructuring, see CRS electronic briefing book.
2. (back) 16U.S.C.§791a-825r. For
text of the FPA, see http://www.ferc.fed.us/intro/acts/fpa.htm.
3. (back)15 U.S.C. § 79 et seq.
4. (back)16 U.S.C. §2601, P.L. 95-617
(1978).
5. (back)The other parts of the
energy package were: 1) Natural Gas Policy Act, P.L. 95-621
(1978); 2) Power Plant and Industrial Fuel Use Act, P.L. 95-620
(1978); 3) National Energy Conservation Policy Act, P.L. 95-619
(1978); 4) Energy Tax Act, P.L. 95-618
(1978).
6. (back)For additional discussion
on PURPA and restructuring, see CRS Report 98-419 ENR.
7. (back)Cogeneration is the
production of electric energy along with steam heat or some other useful form of energy.
8. (back)16 U.S.C. § 824a-3.
9. (back)16 U.S.C.§ 824a-3(b).
10. (back)Historically,
electricity service has been defined as a natural monopoly, meaning that the industry has
(1) an inherent tendency toward declining long-term costs, (2) high threshold investment,
and (3) technological conditions that limit the number of potential entrants.
11. (back)P.L. 102-486
(1992).
12. (back)See CRS Report RL30008
(pdf), Electricity Restructuring: Comparison of H.R. 667 and S. 516.
13. (back)Edison Electric
Institute. Capacity and Generation: Non-Utility Sources of Energy, 1998 edition.
Washington, D.C. p. 5.
14. (back)See U.S. CONST. art. I,
§ 10, cl. 1. See also Yankee Atomic Electric Company v. United States, 112 F.3d
1569, 1577 (Fed. Cir. 1997).
15. (back)See Robert Meltz, When
the United States Takes Property: Legal Principles, CRS Report 91-339A, March 22,
1991.
|